GE Go EleutheraThe island, end to end
Building on Eleuthera

Six steps, four departments, and one deadline that catches everybody.

You will need a permit for all of it — a new house, an addition, an alteration, and also a deck, a shed, a retaining wall or a fence. That is the Buildings Regulations Act and it is not negotiable.

White clapboard house with a covered porch, Eleuthera
Clapboard and a deep porch, 1989 — built for shade and hurricanes, long before anybody called it a style.Rüdiger Stehn · CC BY-SA 2.0 · source
01

Drawings, signed by people on the register

Architectural drawings must be signed by an architect registered with the Bahamas Professional Architects Board. Mechanical and electrical drawings must be signed by a registered engineer. A drawing signed by somebody not on the register does not start the clock — it stops it.

02

Apply, and pay a tenth up front

The application goes to the Ministry of Works & Urban Development, or on a Family Island to the local administrator. A deposit of 10% of the estimated permit fee is payable when you submit.

03

Four departments look at it, not one

Civil Design checks drainage and road access. Physical Planning checks zoning. Environmental Health and the BEST Commission assess environmental impact. The Buildings Control Division checks structural, mechanical and electrical. Any one of them can send it back.

04

Six to eight weeks, from complete

The stated processing time is six to eight weeks after all documents are submitted. Read 'complete' strictly: the clock starts when nothing is missing, not when you first hand something in. This is where most delay actually happens.

05

Collect it locally, pay the balance

On a Family Island you collect the approved permit and settle the balance at the local government office rather than in Nassau.

06

Eighteen months, then it lapses

A permit is valid for eighteen months from issue. An extension must be applied for BEFORE it expires — not after. On an island where a container can be late by a season, this is the deadline that catches people.

What the process does not tell you

Four things worth knowing before you start.

What it costs to build, honestlyWe are not publishing a per-square-foot figure. The number that circulates online traces back to old forum posts and we could not verify a current one, and a stale construction cost is worse than none — you would budget on it. What is true and worth planning around: almost every material arrives by boat, so freight and timing sit inside every line of a quote here in a way they do not at home. Get three real quotes from builders working on this island now.
Duty exemption exists, and it expiresCustoms duty exemptions can apply to imported materials in defined cases. Where one is granted it runs for one year — and if it is approved in December it still ends on 31 December of that same year, not the following December. Time the application to the build, not the other way round.
The exterior is not yours aloneA building permit and Town Planning Committee approval are required for any material change to the exterior of a building — modification, addition, demolition — whether or not the building is historic. Repainting a shutter is not this; changing the shape of the thing is.
Approval to own before approval to buildA non-Bahamian buying more than two acres needs government approval on the purchase itself, which is a separate matter from the building permit and sits before it in the order. See the buying guide.

Sources

Checked 2026-09-10. Government process changes — confirm with the Ministry or your local administrator before you rely on a date. Nothing here is legal or professional advice.

Costing a build here? We introduce you to a BREA-licensed Bahamian brokerage that knows which lots come with which problems — setbacks, access, water, and what the neighbours already tried. No fee to you.
The introduction

Tell us what you're doing.

Six questions. It goes straight to the licensed Bahamian brokerages that cover what you're after — the first to pick it up gets in touch with you directly.

Your details are not shown to anybody until a brokerage claims the introduction, and only then to the one that claimed it. We are not your agent and we take no fee from you.